| Come along
with us while we build Oak Hill, a
new home on a 10 acre parcel in The Woods in Geneva
National Resort. Starting August of 2007, MD properties
will demonstrate our care and philosophy behind each
step of the home building process, creating a new home
that will last for generations, looking and living as
well 10 years from now as it did the day you moved in. |
| |
Click on any
image below for a larger version. |
Obtain proper local and community approvals
for drainage plans, building plans and landscape plans. |
|
| |
|
Apply for building permits. |
|
| 07-14-07 |
 |
Before selecting and clearing trees for
the building site, we met with the home owner, site
superintendents, utility companies, excavators,
landscape architects, water drainage specialists, forest
preservationists, and arborists to determine the best
building site while preserving the maximum number of
trees. If applicable, contact your community
association for permission to clear trees. |
|
| 7-24-07 |
 |
Lot is cleared. Trees
removed. Stumps ground out. |
|
| 7-29-07 |
 |
Top soil is scraped and set
aside for final landscaping - a
Green Built Home
Practice™ |
|
| 8-3-07 |
 |
Preparing the building site
according to Green Guidelines. Demarcate limits of
clearing and grading. Create construction "no
disturbance" zones using fencing or flagging to protect
vegetation and sensitive areas from construction
vehicles, material storage, and washout. |
|
| 8-4-07 |
 |
We engaged an arborist to
conduct deep root fertilization to protect trees near
the building site. Deep root fertilization is a process
where a high quality nutrient solution is injected into
the root zone of trees. The materials are injected into
the root zone under pressure which helps aerate or
provide much needed oxygen to the root system. The soil
injection begins just below the surface and goes to a
depth of 12
– 14 inches. |
|
| 8-5-07 |
 |
Minimize disturbance of and
damage to trees and other vegetation designated for
protection through installation of fencing and avoidance
of trenching, significant changes in grade, and
compaction of soil and critical root zones. Prepare
designated existing trees and vegetation for the impacts
of construction through pruning, root pruning,
fertilizing, and watering. Fence off trees to prevent
the weight of building crew trucks from
damaging the existing root systems, a
Green Built Home
Practice™ |
|
| 8-5-07 |
 |
Install and maintain
sediment and erosion controls, a
Green Built Home
Practice™ |
|
| 8-6-07 |
 |
Reduce soil compaction from
construction equipment by laying mulch, chipped wood, or
plywood sheets. We use chips from the
building's site ground up limbs and stumps to further
protect adjacent trees, a
Green Built Home
Practice™ |
|
| 8-9-07 |
 |
Excavation |
|
| 8-10-07 |
 |
Lay gravel base to support
construction traffic. |
|
| 8-10-07 |
 |
Install track pad. Cut the base
in the site of the final
driveway - lay with track pad to reduce the tracking of
mud onto local street be construction crew vehicles - a
"nice neighbor" practice. |
|
| 8-12-07 |
 |
Pour footings. We use the form-a-drain-system. Form A Drain is a patented, all-in-one,
stay in place, system that forms the foundation footing,
provides drainage and can be adapted to provide a
sub-slab radon reduction system. In addition to
providing a superior footing, Form A Drain creates an
ideal drainage system, one that is parallel to the
footing and below the foundation wall. |
|
| 8-15-07 |
 |
Basement walls set up for
pouring. |
|
| 8-17-07 |
 |
Wall set up continues |
|
| 8-15-07 |
 |
Frost walls installed. |
|
| 8-15-07 |
 |
Form A Drain system
installed along with foundation. |
|
| 8-16-07 |
 |
Begin pouring foundation
walls. Continuous (stem wall) foundations are
constructed poured concrete, supported by a continuous,
reinforced-concrete spread footing. |
|
| 8-17-07 |
 |
Foundation walls complete. |
|
| 8-7-07 |
 |
Supports for future air
conditioning units are installed. |
|
| |
|
|
|
| 8-21-07 |
 |
Insulate exterior
foundation walls. |
|
| 8-22-07 |
 |
Backfill footings. Although
most building codes only require 12", we use from 2 to 3 feet of gravel. |
|
| 8-22-07 |
 |
Lay gravel for basement
floor. Due to the use of supporting grade beams, this
floor will be poured earlier than usual in the building
schedule. |
|
| 8-24-07 |
 |
Trenching basement floor drains to
alleviate ground water build up during and after
construction, and to protect nearby trees from excess
water run off, a
Green Built Home
Practice™ |
|
| 8-24-07 |
 |
Installation of
sewer drain. |
|
| 8-24-07 |
 |
Sewer drain complete. |
|
| 8-24-07 |
 |
Foundation inspection by Abbey, local
Cairn Terrier. Foundation approved. |
|
| 8-27-07 |
 |
Install rough plumbing in foundation
prior to grade beams. |
|
| 8-28-07 |
 |
We installed grade beam footings to help
support the load of wide flooring spans and to
facilitate the installation of heating ductwork later in
construction. A grade beam footing is a continuous
reinforced-concrete member used to support loads with
minimal bending and are capable of spanning across
non-load bearing areas.
|
|
| 8-30-07 |
 |
Basement crushed stone was graded and
compacted. Then a vapor barrier was placed to cover the
entire basement area. 2" Styrofoam was then placed on
top to reduce thermal heat loss. |
|
| 8-31-07 |
 |
In-floor heating tubes were installed in
preparation for an on-demand hot water system, a
Green Built Home
Practice™ |
|
| 8-31-07 |
 |
More prep for on demand hot
water system. |
|
| 9-4-07 |
 |
Pouring the basement floor. |
|
| 9-04-07 |
 |
Basement floor poured and
soft cut, then sealed the following day. |
|
| 9-05-07 |
 |
Foundation is backfilled
with stone |
|
| 9-6-07 |
 |
Foundation backfill
complete- delayed due to
heavy rains. |
|
| 9-18-07 |
 |
Lower level framed. |
|
| 9-18-07 |
 |
Foundation is capped. |
|
| 9-20-07 |
 |
Main floor layout. |
|
| 9-2007 |
 |
Framing |
|
| 9-2007 |
 |
Framing |
|
| 9-2007 |
 |
Framing |
|
| 10-3-07 |
 |
Framing |
|
| 10-17-07 |
 |
Framing |
|
| 10-20-07 |
 |
Framing |
|
| 10-20-07 |
 |
Framing |
|
| 10-23-07 |
 |
Framing |
|
| 10-23-07 |
 |
Framing |
|
| 10-23-07 |
 |
Framing |
|
| 10-23-07 |
 |
We only use TimberStrand
when constructing rooms with 10' walls. TimberStrand is an
engineered lumber that is always straight, true and
consistent. It is free of knots and resists twisting,
shrinking and bowing after installation. This helps
reduce sheetrock cracks. Cabinets and countertops
install flush without the hassles of shimming. Reduces
the chance of tile and grout cracking. Framing
inspection by Brianna. |
|
| 11-19-07 |
Adams_small.jpg) |
Framing continues. Windows
are being installed. |
|
| 11-20-07 |
 |
Front stoop is poured. |
|
| 11-20-07 |
 |
Garage is poured |
|
| 11-20-07 |
 |
Zero-step access garage
entrance is completed -
a barrier free, universal
design principal. |
|
| 11-22-07 |
 |
Exterior brick goes up. |
|
| 11-26-07 |
 |
Chimneys run with brick. |
|
| 11-26-07 |
 |
Rough plumbing begins. |
|
| 11-27-07 |
 |
Bath tubs are installed and
protected with wood caps. |
|
| 11-29-07 |
 |
Copper Chimney Caps
Installed |
|
| 11-29-07 |
 |
Fireplaces are installed |
|
| 12-1-07 |
 |
Front entrance is laid with
brick. |
|
| 12-10-07 |
 |
Stone sills are installed. |
|
| 12-05--07 |
|
Rough electric begins |
|
| 12-05-07 |
 |
Window installation almost
complete. Roofing 75% complete |
|
| 12-14-07 |
 |
Roofing is finished. |
|
| 12-14-07 |
 |
Blocking for grab bars -
a barrier free
universal design principal |
|
| 12-17-07 |
 |
Exterior siding begins. As
an extension of the Universal Design Principal, this
home is finished with HardiPlank and
HardiShingles, offering the
longevity and low maintenance of Engineered Cement
Composite to reduce
future maintenance requirements. |
|
| 1-19-08 |
 |
Exterior framing complete.
1 degree below zero! |
|
| 1-19-08 |
 |
Front entry nears
completion. |
|
| 1-19-08 |
 |
Interior cleaned up and
ready for inspections. All systems passed inspection!
Dry wall is next. |
|
\
| 1-27-08 |
 |
Front entry complete. |
|
| 1-27-08 |
 |
We used Azek beadboard to
finish off the barrel roll ceiling on the front entry to
reduce cracking and warping. |
|
| 1-28-08 |
 |
Lower level ceilings
insulated with R-19. |
|
| 2-2-08 |
 |
Exterior walls insulated
with R-21. |
|
| 2-15 |
 |
R-50 Attic insulation complete. |
|
| 2-22 |
 |
Drywall installation and
taping complete. |
|
| |
 |
Home is prepped for drywall
spray. |
|
| 2-26 |
 |
Drywall textures being
applied. |
|
| 2-27 |
 |
Drywall wall finishes
complete. |
|
| 3-5-08 |
 |
Walnut flooring installation begun |
|
| 3-6-08 |
 |
Walnut flooring
installation almost complete |
|
| 3-7-08 |
 |
Doors are delivered. |
|
| 3-7-08 |
 |
Millwork is delivered. |
|
| 3-11=08 |
 |
Custom cabinet delivery |
|
| 3-12-08 |
 |
Cabinet installation begins |
|
| 3-12-08 |
 |
Windows are being prepped
for staining and painting. |
|
| 3-18-08 |
 |
Mechanicals are under way. |
|
| 3-19-08 |
 |
Cabinet installation
continues. |
|
| 3-25-08 |
 |
Tile installation begins. |
|
| 3-29-08 |
 |
Tile installation
continues. |
|
| 3-30-08 |
 |
Tile installation
continues. |
|
| 4-9-08 |
 |
Custom stain colors are
tested and selected. |
|
| 4-10-08 |
 |
Lower level interior doors
are hung. |
|
| 4-11-08 |
 |
Exterior wood decking is
installed using hidden fasteners. |
|
| 4-18-08 |
 |
Great room beam
installation begins. |
|
| 4-19-08 |
 |
Maintenance free Azek is
installed as under-decking, with screening above to
protect against insects in porch above.. |
|
| 4-19-08 |
 |
Tile installation
continues. |
|
| 4-22-08 |
 |
Tile installation
continues. |
|
| 4-27-08 |
 |
Finish carpentry continues. |
|
| 4-27-08 |
 |
Master shower tile
installed. |
|
| 4-28-08 |
 |
Great room beams are
completed. |
|
| 4-29-08 |
 |
Upper level doors are
installed. |
|
| 4-29 |
 |
Master bedroom beams are
completed. |
|
| 4-30-08 |
 |
Front doors are installed. |
|
| 4-30-08 |
 |
Stair construction begins. |
|
| 4-30-08 |
 |
Counter tops are measured. |
|
| 5-2-08 |
 |
Upper level slated being installed. |
|
| 5-2-08 |
 |
Finish carpentry inspection by Brianna. |
|
| 5-2-08 |
 |
Stair balusters are positioned using
lasers. |
|
| 5-3-08 |
 |
Final crown molding
installed. |
|
| 5-6-08 |
 |
Painters prepare for
painting the doors. |
|
| 5-15-08 |
 |
Painters prep upper level
windows. |
|
| 5-15-08 |
 |
Upper level slate is
grouted. |
|
| 5-19-08 |
 |
Great room beams are
stained. |
|
| 5-27-08 |
 |
Master bath tub surround
installed. |
|
| 5-27-08 |
 |
Painting continues. |
|
| 5-27-08 |
 |
Wood-finishing continues. |
|
| 5-27-08 |
 |
Master-tub-mechanicals
access installed. |
|
| 6-4-08 |
 |
Fireplace stone
installation begins in the hearth room. |
|
| 6-04-08 |
 |
Upper floors are covered in
preparation for the painters. |
|
| 6-4-08 |
 |
Great room fireplace is
stained, the surround is installed, and covered in
preparation for the painters. |
|
| 6-4-08 |
 |
Master bedroom beams are
stained. |
|
| 6-4-08 |
 |
Preparation for installing
the exterior stone fireplace. |
|
| 6-4-08 |
 |
Master shower grout
complete. |
|
| 6-4-08 |
 |
Master tub surround
complete. |
|
| 6-4-08 |
 |
Hearth room stone surround
complete. |
|
| 6-4-08 |
 |
Exterior fireplace stone
complete. |
|
| 6-5-08 |
 |
Lower level trim and doors
painted. |
|
| |
|
|
|